Section 151.23.011 Building Permits
For the purpose of implementing a PAD, building permits may be issued for buildings and structures in the area covered by the approved Final PAD Plan if they are in conformity with the Final PAD Plan and with all other applicable ordinances and regulations.
   1.   Once a Final PAD Plan has been approved and recorded, it can be amended, changed or modified only through the procedure prescribed herein for the initial application for approval.
   2.   A development schedule for residential uses may be submitted as part of the project plan, and the construction and provision of all of the common open spaces and public recreational facilities which are shown on the Final PAD Plan must proceed at the same rate as the construction of dwelling units. If the Director of Community Development should find that the rate of dwelling unit construction is greater than the rate at which common open areas and public and recreational facilities are being constructed or provided, he shall notify the developer that no permits for dwelling unit construction will be issued until the rate of construction conforms to the development schedule.
   3.   The development schedule may provide for staged construction of the Final PAD Plan. Building permits will not be issued for any stage of the final plan unless the common open space allocated to that stage by the development schedule has been conveyed to the appropriate parties.
(Ord. 743, passed 4-10-86)