Section 151.18.009 Completion of Project Documents
A.   As-built drawings will be required for storm detention basin input and output structures as determined by the City.
B.   Site work that is not completed to the City’s satisfaction, will require, prior to the issuance of a final certificate of occupancy, a security totaling 110 percent of the estimated cost to complete the improvement. An estimate of the remaining work shall be provided to and approved by the City.
C.   Upon completion of the improvement, the City shall return the security to the Developer.
(Ord. 2008-010, passed 5-8-08; Am. Ord. 2018-002, passed 2-8-18; Am. Ord. 2023-003, passed 4-6-23)