§ 155.40 PERIMETER CONTROL PLAN.
   The permittee shall secure the perimeter prior to any land disturbance to decrease off-site sedimentation once construction begins.
   (A)   Control plan objectives.
      (1)   Focus on downstream points and outfall areas and does not necessitate protection of the entire site boundary;
      (2)   Protect adjacent properties by the use of vegetated strips along lower perimeters, sediment barriers, filters, diversion berms, sediment basins or other means acceptable to the city;
      (3)   Protect all points of discharge from outlets such as pipes, drains, culverts, conduits and channels;
      (4)   Minimize erosion and control sedimentation; and
      (5)   Reduce the velocity of flows from the project site.
   (B)   Control plan requirements.
      (1)   The permittee shall utilize sediment control measures that consider the type of flow, site terrain, soil type and other relevant factors;
      (2)   Buffer strips may only be utilized for sheet flow;
      (3)   Supplemental control measures shall be utilized when a single control device or measure proves ineffective; and
      (4)   Location and description of construction entrances and exits that comply, or exceed, with BMP minimum standards.
(Ord. 012-100, passed 4-9-2012)