10-1-2: BUILDING PLAN REVIEW:
   A.   The building official shall be responsible for plan review coordination and for issuance of building permits.
   B.   Upon application by any person for a building permit, the building official shall review the plans for compliance with the applicable building or technical codes. The building official shall submit the plans to any other affected city department for review and approval by the department before issuance of a permit.
   C.   Building plan review shall be completed by the building official within thirty (30) working days of submittal by the applicant.
   D.   The building official may, in proper cases, request the aid of the building codes bureau (or its successor), other state agencies, or professional consultants to aid in coordination of review. In such cases, the building official may lengthen the completion time for review as deemed necessary. (Ord. 803, 9-20-2010)