1367.10 RESTORATION OF SURFACE OF PAVED STREETS.
   (a)   In all sidewalks, driveways, streets or parts of streets that are paved or macadamized, all the backfilling shall be well-compacted by jetting. After the trench has been backfilled and jetted to the required height, the subgrade for the new paving shall be further compacted by rolling the backfill at paving subgrade elevation. The pavement shall then be relaid carefully and thoroughly to the section and of the materials specified. If not specified, then the replacement shall be to the section and of the materials originally placed and to the satisfaction of the Engineer.
   (b)   When the work is completed, all surplus material, earth, rubbish, etc., shall be removed and that portion of the surface of each street disturbed by construction shall be left in as good condition as it was before the commencement of the work, and it shall be promptly and regularly maintained in such condition during a period of one year after the acceptance of the work.
(Ord. 352. Passed 10-22-62.)