1365.25 SPECIAL REQUIREMENTS.
   (a)   The contractor shall remove and replace all pavement within the lines of excavation. The term pavement shall mean a hard surface for either streets or driveways. After the backfill has been completed, the contractor shall furnish, place and maintain, wherever a pavement has been removed, a temporary surface which will provide a safe and passable roadway until the final pavement has been completed.
   (b)   All final repaving or surfacing shall be done in accordance with the specifications of the plans, or as may be required by the Ohio Department of Transportation, or as directed by the Engineer. The final repaving shall be done with the same type of material as that removed or, if such is not available or satisfactory for any reason, then with a type of material and construction that is satisfactory to the Engineer.
(Ord. 352. Passed 10-22-62.)