(a) All pavements, road surfaces, sidewalks, driveways or curbs which were in place before the work was started shall be replaced in the same manner as the original installation, or as specified by the Engineer, and the cost of such replacement shall be borne by the contractor unless otherwise specified.
(b) All road surfaces, walks and driveways that had a hard surface material other than blacktop or concrete shall be replaced with a material meeting the requirements of Item 310 of the State of Ohio Department of Transportation Construction and Material Specifications, as amended. The material will be placed in layers and shall be thoroughly compacted. Road surfaces shall be compacted by means of an approved roller weighing not less than ten tons.
(Ord. 352. Passed 10-22-62.)