(a) Upon completion of backfilling, or before completion if so ordered by the Engineer, the contractor shall remove from the site of the work all surplus material, tools, equipment and construction sheds.
(b) All surplus excavated material shall be removed and deposited upon lands abutting the improvement if such fill is requested by the property owners. If no filling of abutting property is desired, the contractor shall dispose of such surplus excavation wherever he or she can arrange for rights to fill.
(c) The street and all environments shall be left clean and in as good repair or better than they were before the work was begun.
(Ord. 352. Passed 10-22-62.)