1359.04 PREPARATION OF EXCAVATIONS.
   When excavations are opened up, if, in the opinion of the Engineer, the materials in place are not adequate for structural stability of the completed work, the Engineer may order the contractor to carry the excavation to an additional depth and/or furnish and place concrete cradles, sand or gravel refill and/or timber and piling foundations.