(A) See town fee schedule for fore prevention temporary power inspections.
(B) Temporary power shall be requested by the project contractor or other appointed representative. The Fire Code Official will inspect the project for compliance with temporary power requirements and issue temporary power for 30 days. In the event that a time extension is needed it is the responsibility of the project contractor to or other appointed representative to request for a temporary power extension which will be issued for an additional 30 days. In the event that a temporary power becomes expired the project contractor or other appointed representative will be contacted by the Fire Code Official informing them that the temporary power is expired and they need to request an extension. Failure to request temporary power extension after being notified will result in power being pulled from Brunswick Electric Membership Corporation personnel. These fees address temporary power inspections.
(Ord. 10-11, passed 7-6-2011; Ord. 14-17, passed 12-2-2014)