§ 55.055 APPLICABILITY AND EXEMPTIONS.
   (A)   The Town of Sellersburg will require a Stormwater Pollution Prevention Plan (SWPPP), which includes erosion and sediment control measures and materials handling procedures, to be submitted as part of a project’s construction plans and specifications. Any project located within the corporate boundaries of the Town of Sellersburg that includes clearing, grading, excavation or other land disturbing activities resulting in the disturbance of 10,000 square feet or more of total land area is subject to the requirements of this subchapter. This includes both new development and re-development. This subchapter also applies to disturbances of land that are part of a larger common plan of development or sale if the larger common plan will ultimately disturb 10,000 square feet or more of total land area. Section 55.057 provides guidelines for calculating land disturbance. Projects meeting the coverage requirements of 327 IAC 15-5 (Rule 5) shall also be in compliance with 327 IAC 15-5.
   (B)   The requirements under this section do not apply to the following activities:
      (1)   Agricultural land disturbing activities; or
      (2)   Forest harvesting activities.
   (C)   The requirements under this section do not apply to the following activities, provided other applicable state permits contain provisions requiring immediate implementation of soil erosion control measures:
      (1)   Landfills that have been issued a certification of closure under 329 IAC 10;
      (2)   Coal mining activities permitted under I.C. 14-34; and
      (3)   Municipal solid waste landfills that are accepting waste pursuant to a permit issued by the Indiana Department of Environmental Management under 329 IAC 10 that contains equivalent stormwater requirements, including the expansion of landfill boundaries and construction of new cells either within or outside the original solid waste permit boundary.
   (D)   For an individual lot where land disturbance is expected to be one acre or more, the individual lot owner must complete their own notice of intent letter, apply for a stormwater permit from the town, and ensure that a sufficient construction and stormwater pollution prevention plan is completed and submitted in accordance with §§ 55.080 et seq. regardless of whether the individual lot is part of a larger permitted project site.
   (E)   An individual lot with land disturbance less than 10,000 square feet, located within a larger permitted project site, is considered part of the larger permitted project site, and the individual lot operator must comply with the terms and conditions of the stormwater permit approved for the larger project site. The stormwater permit application for the larger project site must include detailed erosion and sediment control measures for individual lots.
   (F)   It will be the responsibility of the project site owner to complete a stormwater permit application and ensure that a sufficient construction plan is completed and submitted to the town in accordance with §§ 55.080 et seq. It will be the responsibility of the project site owner to ensure compliance with this chapter during the construction activity and implementation of the construction plan, and to notify the town with a sufficient notice of termination letter upon completion of the project and stabilization of the site. However, all persons engaging in construction and land disturbing activities on a permitted project site meeting the applicability requirements must comply with the requirements of this section and this chapter.
(Ord. 2021-OR-003, passed 1-11-21)