§ 35.111 APPLICATION; PROCESS.
   (A)   This section applies whenever a public work project is estimated to cost less than $50,000. Except as provided in this chapter for local Boards of Aviation Commissioners and local airport authorities, if a contract is to be awarded, the Board may proceed under divisions (B) or (C).
   (B)   The Board must proceed under the following provisions:
      (1)   The Board shall invite quotes from at least three persons known to deal in the class of work proposed to be done by either of the following:
         (a)   Mailing them a notice stating that plans and specifications are on file in a specified office. The notice must be mailed not less than seven days before the time fixed for receiving quotes. The Board may not require a person to submit a quote before the meeting at which quotes are to be received. The meeting for receiving quotes must be open to the public. All quotes received shall be opened publicly and read aloud at the time and place designated and not before.
         (b)   Soliciting at least three quotes by telephone, facsimile transmission, or electronic mail. The seven day waiting period required by division (a) does not apply to quotes solicited under this clause. A quote received under this clause shall be reported to the Board during the public meeting at which the contract is considered. The name of each person submitting a quote, and the amount of each quote, shall be read aloud at the public meeting.
      (2)   The Board shall award the contract for the public work to the lowest responsible and responsive quoter.
      (3)   The Board may reject all quotes submitted.
      (4)   If the Board rejects all quotes under division (3), the Board may negotiate and enter into agreements for the work in the open market without inviting or receiving quotes if the Board establishes in writing the reasons for rejecting the quotes.
   (C)   The Board may not proceed under division (B) for the resurfacing (as defined in I.C. 8-14-2-3) of a road, street, or bridge, unless:
      (1)   The weight or volume of the materials in the project is capable of accurate measurement and verification; and
      (2)   The specifications define the geographic points at which the project begins and ends.
   (D)   For the purposes of this section, if contiguous sections of a road, street, or bridge are to be resurfaced in a calendar year, all of the work shall be considered to comprise a single public work project.
   (E)   The Board may purchase or lease supplies in the manner provided in I.C. 5-22 and perform the public work by means of its own workforce without awarding a public work contract.
   (F)   Before the Board may perform any work under this section by means of its own workforce, the political subdivision or agency must have a group of employees on its staff who are capable of performing the construction, maintenance, and repair applicable to that work.
(Res. 2020-R-004, passed 5-26-20)