(a) A certificate of occupancy shall be applied for and approved by the Planning Commission before any building permit is issued for the construction or change in use of a building or use of land in any Industrial Park District.
(b) An application for a certificate of occupancy for a building or use of land shall be accompanied by:
(1) A plot plan of the land or parcel of land to be used, showing dimensions, location of all existing and proposed buildings, driveways, off-street parking areas, topography, abutting streets, railroads, highways, loading and unloading areas, watercourses and other topographic features within 200 feet of the property lines.
(2) Architectural plans for all proposed buildings, walls and fences.
(3) A description of the proposed industrial operation in sufficient detail to fully describe the nature and extent of the proposed use.
(4) Plans or reports describing proposed treatment of any excess traffic conditions, noise, glare, air pollution and treatment or handling of hazardous gases, liquids or other material.
(5) Plans or reports showing proposed treatment and disposal of sewage and industrial wastes.
(6) A description of any fuel proposed to be used, including engineering plans for the control of any smoke which may be generated.
(7) Additional data which may be required by the Planning Commission to ascertain conformance with the requirements of the Zoning Ordinance.
(c) A change or changes in the physical facilities or use permitted by a certificate of occupancy shall occur only after the holder of such certificate has obtained an amendment thereto allowing such change or changes.
(d) A certificate of occupancy for a building or use of land in an Industrial Park District may be revoked by the Planning Commission after a hearing, if the commission finds that the holder of the certificate has failed to comply with the development of approved plans.
(Ord. 846-64. Passed 9-3-64.)