§ 25-23-10 PERMIT; REQUIRED AND EXCEPTIONS.
   (A)   Permit required. It shall hereafter be unlawful to erect, construct, reconstruct, repair, or establish any building, transmission line, pole, tower, chimney, wires, or any other structure or appurtenance within the hazard area without first obtaining a permit from the Development Services Department upon a form furnished by it. Any application shall be promptly considered and granted or denied. Applications for action by the Board of Adjustment shall be transmitted in accordance with the applicable provisions of the airport zoning regulations, appropriate city and/or county ordinances, and/or state law. It shall also be unlawful to plant or replant any tree or other object of natural growth without the necessary permit.
   (B)   Permit exceptions. Within the outer area of the approach zones and within the turning zones, no permit shall be required for any construction or planting that is not higher than 75 feet above the nearest existing or proposed runway end. The repair, reconstruction, or replacement of nonconforming electric facilities will be permitted in compliance with Neb. RS 3-311(3).
   (C)   Location sketch and zoning map. The boundaries, approach zones, operations zone, transition zones, and turning zones of the airport are indicated on the zoning map that accompanies and is made a part of this article by reference. A copy of the airport hazard area zoning regulations shall at all times be on file in the office of the Airport Director located at Western Nebraska Regional Airport.
(Ord. 4173, passed - -2015)