§ 24-3-23 CHANGES DURING CONSTRUCTION REPORTS.
   The permittee shall maintain records with the SWPPP under the following circumstances along with recommendations for corrective measures, if deemed necessary and appropriate:
   (A)   There are delays in obtaining materials, machinery, services, or manpower necessary to the implementation of the grading, or SWPPP as scheduled;
   (B)   There are delays in land disturbing or filling activities or soil storage;
   (C)   The work is not being done in conformance with the approved grading or SWPPP;
   (D)   There are any departures from the approved grading plan which may affect implementation of the SWPPP as scheduled;
   (E)   There are any delays in the implementation of the SWPPP plans; and
   (F)   There are any other departures from implementation of the SWPPP.