§ 53.071  TENTATIVE DETERMINATION AND DRAFT PERMIT.
   (A)   The POTW staff shall conduct a review of the application and an on-site inspection of the significant industrial user, including any pretreatment facilities, and shall prepare a written evaluation and tentative determination to issue or deny the significant industrial user permit.
   (B)   If the staff’s tentative determination in division (A) above is to issue the permit, the following additional determinations shall be made in writing:
      (1)   Proposed discharge limitations for those pollutants proposed to be limited;
      (2)   A proposed schedule of compliance, including interim dates and requirements, for meeting the proposed limitations; and
      (3)   A brief description of any other proposed special conditions which will have significant impact upon the discharge described in the application.
   (C)   The staff shall organize the determinations made pursuant to divisions (A) and (B) above and the town’s general permit conditions into a significant industrial user permit.
(Ord. passed 9-27-1994)