§ 154.088 LIMITATIONS ON VALIDITY OF PERMIT.
   (A)   Construction must be initiated under a special land use permit within one year from date of issuance of the permit. Upon receipt of a written request for an extension an extension of up to one year may be granted by the Planning Commission if the Planning Commission feels the nature of the problems preventing project initiation are legitimate, and that the approved site plan adequately represents current conditions on and surrounding the site.
   (B)   If the project is not initiated within an approved period the special land use is cancelled. Thereafter, the project may proceed only if approved after going through the entire special land use process again, starting with a new application.
(Ord. passed 6-24-1996; Am. Ord. 02-02, passed 2-11-2002)