(A) As excavation work progresses, all streets shall be thoroughly cleaned of all rubbish, excess earth, rock and other debris resulting from such work. All cleanup operations at the location of each excavation shall be accomplished at the expense of the permittee and shall be completed to the satisfaction of the Director of Public Works. All roadside drainage ditches shall be restored to a true grade and the intake and outlet ends of all culverts shall be left free from all excess materials and debris. As may be ordered by the Director of Public Works and in any event immediately after completion of such excavation work, the permittee shall clean up and remove all refuse and unused materials of any kind resulting from such work and upon failure to do so within 24 hours after having been notified to do so by the Director of Public Works, such work may be done by the Director of Public Works and the cost thereof charged to the permittee.
(B) Violation of this section shall be deemed an infraction.
('64 Code, § 19-59) (Ord. 164, passed 12-20-60) Penalty, see § 10.97