(A) Whenever any permittee holding a construction permit has completed any work for which a permit has been granted, he shall so notify the Director of Public Works in writing within 15 days after completion of work. If, after the Director of Public Works, or his duly authorized representative has, by survey, inspection or both found that the work has been completed in accordance with the requirements of the permit issued therefor and all the provisions of this subchapter, he shall issue, if requested by the permittee, a certificate of acceptance which shall contain a statement of the location, nature and total amount of the work performed under such construction permit.
(B) Violation of this section shall be deemed an infraction.
('64 Code, § 19-75) (Ord. 164, passed 12-20-60) Penalty, see § 10.97