§ 112.029 ACCESS TO PREMISES.
   In the case of new construction or property development where utilities are to be placed underground, the developer or property owner shall give a grantee reasonable notice of not less than 30 days prior to such construction or development, and of the particular date on which open trenching will be available for a grantee's installation of conduit, pedestals and/or vaults, and laterals to be provided at a grantee's expense. A grantee shall also provide specifications as needed for trenching. Cost of trenching and easements required to bring service to the development shall be borne by the developer or property owner.