Within two years of Administrative or Development Permit approval, commencement of construction shall have occurred or the permit shall become null and void. In addition, if after commencement of construction, work is discontinued for a period of one year, then the Administrative or Development Permit shall become null and void. Projects may be built in phases if preapproved by the review authority. If a project is built in preapproved phases, each subsequent phase shall have one year from the previous phase's date of construction commencement to the next phase's date of construction commencement to have occurred, or the Administrative or Development Permit shall become null and void.