17.228.440   Temporary recycling at manufacturing facilities.
Temporary recycling operations at manufacturing facilities are permitted with a zoning administrator's conditional use permit in the C-4, M-1, M-2, M-1(S), and M-2(S) zones. Temporary operations must meet the criteria in this section.
   A.   One temporary permit will be issued for a maximum of 90 days per calendar year for a site qualifying as a manufacturing site. No extensions of time will be permitted per site per calendar year.
   B.   The proposed site for the temporary permit shall comply with all recycling operation standards in section 17.228.410.
   C.   All equipment brought in for the temporary recycling operations shall be removed on or before the last day of the temporary permit.
   D.   Recycling operations are limited to the recycling of on-site materials that result from normal business operations conducted on the site. Off-site materials are not allowed to be accepted for recycling during the temporary recycling period granted. (Ord. 2013-0020 § 1; Ord. 2013-0007 § 1)