17.228.400   Recycling facility-General.
   A.   Zones and permit required. Recycling facilities are permitted in the zones listed in the table below, subject to the permit specified and the other requirements of this chapter:
 
Type of Facility
Zones Permitted
Permit Required
Convenience recycling facility
SC, C-1, C-2, C-3, C-4, M-1, M-2, M-1(S), M-2(S), M-T
Administrative permit
Minor recycling facility
C-4, M-1, M-2, M-1(S), M-2(S), M-T
Zoning administrator conditional use permit
Major recycling facility
C-4, M-1, M-2, M-1(S), M-2(S), M-T
Planning and design commission conditional use permit
Greenwaste facility
A
Zoning administrator conditional use permit
C-4, M-1, M-2, M-1(S), M-2(S), M-T
Planning and design commission conditional use permit
Temporary recycling at manufacturing facility
C-4, M-1, M-2, M-1(S), M-2(S), M-T
Zoning administrator conditional use permit
 
   B.   Permit for multiple sites. A single administrative permit, zoning administrator conditional use permit, or planning and design commission conditional use permit may be approved for more than one facility on more than one site if:
      1.   The operator of each of the proposed facilities is the same;
      2.   The proposed facilities are determined to be similar in nature, size, and intensity of activity; and
      3.   All of the applicable criteria and standards set forth in the development standards or operational standards in this section are met for each such proposed facility. (Ord. 2020-0006 § 7; Ord. 2013-0020 § 1; Ord. 2013-0007 § 1)