A. Front-yard setback. The minimum front-yard setback is 10 feet. There is no maximum front-yard setback.
B. Street side-yard setback. The minimum street side-yard setback is five feet. The maximum street side-yard setback is 25 feet.
C. Interior side-yard setback.
1. Unless paragraph 2 or 3 of this subsection applies, the minimum interior side-yard setback is five feet.
2. If the interior side-yard lot line abuts a public alley, no minimum interior side-yard setback is required.
3. If the interior side-yard lot line abuts a residential zone, the minimum interior side-yard setback is 10 feet.
D. Rear-yard setback.
1. Unless paragraph 2 or 3 of this subsection applies, the minimum rear-yard setback is 15 feet.
2. If the rear lot line abuts a public alley, no minimum rear-yard setback is required.
3. If the rear lot line abuts a residential zone, the minimum rear-yard setback is 25 feet.
E. Levee setback. A minimum 20-foot setback from the landside toe of any flood control levee is required for development less than five acres in size. A minimum 50-foot setback is required from the landside toe of any flood control levee for development five acres or greater in size. No primary or accessory structures may encroach into the levee setback. (Ord. 2017-0061 § 61; Ord. 2013-0020 § 1; Ord. 2013-0007 § 1)