12.20.030   Traffic control plan-Requirements.
   A.   Application. Before approving a traffic control plan, the director shall require a written submission of a proposed traffic control plan that includes the following information:
      1.   The name and business address of the applicant.
      2.   A diagram showing the location of the proposed work area.
      3.   A diagram showing the location of areas where the public right-of-way will be closed or obstructed.
      4.   A diagram showing the placement of traffic control devices necessary to perform the work.
      5.   The proposed phases of traffic control.
      6.   The time periods when the traffic control will be in effect.
      7.   The time periods when work will prohibit access to private property from a public right-of-way.
      8.   A statement that the applicant will comply with the city's noise ordinance during the performance of all work.
      9.   A statement that the applicant understands that the plan may be modified by the director at any time in order to eliminate or avoid traffic conditions that are hazardous to the safety of the public.
   B.   Upon receiving a complete proposed traffic control plan, the director shall either approve, approve with modifications or disapprove the plan.
   C.   If the work to be performed under the approved traffic control plan is not commenced and completed within the times specified in the plan, the plan shall be deemed to have expired, and shall be void, and a new plan shall be required prior to commencing or continuing work.
(Ord. 2002-004 § 3, 2002; Ord. 98-002 § 2; prior code § 25.04.069-2)