A. Any person applying for a building or demolition permit for a covered project shall submit a completed waste management plan (WMP), on a form provided by the city, for approval by the director. The WMP shall indicate the following:
1. The types of C&D debris that will be generated from the covered project;
2. The manner in which C&D debris will be managed and/or stored on the project site;
3. The manner in which recyclable C&D debris generated from the project will be diverted;
4. The person who will haul, collect or transport the recyclable C&D debris from the project site; and
5. The certified C&D sorting facility or recycling facility where recyclable C&D debris will be delivered.
B. No permit shall be issued for any covered project prior to the approval of the WMP by the director. The director shall make a determination within five business days after receipt of the WMP and shall approve a completed WMP that provides all the information required under this section. Approval of the WMP shall not be required where an emergency demolition is necessary to protect the public health, safety and welfare pursuant to Chapter 8.96 of this code.
C. A permit holder shall submit an addendum to the approved WMP for approval by the director if there are any changes to the information provided in the approved WMP during the course of the project. (Ord. 2009-001 § 1)