§ 152.06  VILLAGE’S RESPONSIBILITIES.
   Each erosion and sediment control plan shall be reviewed and acted upon according to the following procedures:
   (A)   Applicant.  As a condition of this section the Village shall require the applicant or designated agent to consult with the Village Engineer on soil erosion and sediment control plans.  The applicant shall submit all required items to the Village and Village Engineer on the same day that the application is made to Village Engineer. 
   (B)   Engineer. The Village Engineer shall:
      (1)   Review the applicant’s soil erosion and sediment control plans and provide written evaluation to the Village regarding the adequacy (effectiveness) to address the provisions of this chapter.  The Village Engineer may retain the services of a Certified Professional in Erosion and Sediment Control (CPESC) to perform the services outlined in this section.  The Village Engineer may assess a fee to the Village to be paid by the applicant for performing these services;
      (2)   Attend a preconstruction meeting with the applicant or designated agent to review implementation of erosion and sediment control plans;
      (3)   Conduct on-site observation during the active construction phases of land development projects to determine whether site development is in compliance with the approved erosion and sediment control plans, and determine adjustments needed to the approved plans.  After construction has been completed, determine whether permanent site stabilization has been achieved and identify operation and maintenance needs;
      (4)   Prepare correspondence as needed regarding effectiveness (or corrective measures needed) or adequacy of soil erosion, and sediment control measures; and
      (5)   Consult with land developers, consultants, and contractors concerning the design criteria, installation and maintenance procedures, and other information regarding conservation practices recommended under the provisions of this chapter.
   (C)   Village. The Village shall:
      (1)   After review, and found to be in conformance with the provisions of this chapter, approve the erosion and sediment control plan;
      (2)   Approve the erosion and sediment control plan subject to such reasonable conditions as may be necessary to secure substantially the objectives of this chapter, and issue the approval subject to these conditions; or
      (3)   Disapprove the erosion and sediment control plan, indicating the deficiencies and the procedures for submitting a revised application and/or submission.
(Prior Code, § 15.6)