§ 1-7-1 FEE SCHEDULE.
Use
Fee
Use
Fee
ANNUAL DOG AND CAT LICENSE FEES
   Neutered males and spayed females
$10
 
 
 
   Unneutered males and unspayed females
$20
 
 
 
BARS AND SALOONS
   Wine
$50
 
 
 
   Beer
$150
 
 
 
   Beer and wine
$200
 
 
 
   All beverages
$250
 
 
 
BUILDING PERMITS
Total valuation of project
   $1 to $1,999
$35 for up to $1,999
   $2,000 to $24,999
$50 for the first $2,000, plus $15 for each additional $1,000
   $25,000 to $49,999
$400.00 for the first $25,000, plus $10 for each additional $1,000
   $50,000 to $99,999
$650 for the first $50,000, plus $7 for each additional $1,000
   $100,000 to $499,999
$1,000 for the first $100,000, plus $6 for each additional $1,000
   $500,000 to $999,999
$3,250 for the first $500,000 plus $5 for each additional $1,000
   $1,000,000 and up
$5,650 for the first $1,000,000, plus $4 for each additional $1,000
Investigation fee
20% of cost of permit if project is over $5,000
SOLICITOR LICENSE
   Week (7 consecutive days)
$75 a week
 
 
 
   Year
$150
 
 
 
SEWER RATE SCHEDULE (MONTHLY)
   3/4 inch base rate fee for 3,050 gallons
$27.44
 
 
 
   1 inch base rate fee for 5,155 gallons
$46.37
 
 
 
   1-3/4 inch base rate fee for 8662 gallons
$77.92
 
 
 
   2 inch base rate fee for 12,841 gallons
$115.75
 
 
 
   3 inch base rate fee for 20,700 gallons
$186.59
 
 
 
   4 inch base rate fee for 28,640 gallons
$257.66
 
 
 
   Additional usage is $2.55 per thousand gallons
SEWER SYSTEM DEVELOPMENT FEE (Note: water line connection size for sewer development fee)
Size
Multiplier
Development Fee
Installation Cost
Total
   3/4 inch
1
$1,045.45
$400
$1,445.45
   1 inch
1.69
$1,766.81
$400
$2,166.81
   1-1/2 inch
2.84
$2,969.08
$400
$3,369.08
   2 inch
4.21
$4,401.34
$400
$4,801.34
   3 inch
6.80
$7,109.06
$400
$7,509.06
   4 inch
9.39
$9,816.78
$400
$1,0216.78
$4,080.90 combined total for 3/4 inch water and sewer development fees
STORM WATER UTILITY (MONTHLY)
   Water/sewer account in the city limits
$5
 
 
 
WATER RATE SCHEDULE (MONTHLY)
   3/4 inch base rate fee for 3,000 gallons
$35.56
 
 
 
   1 inch base rate fee for 5,070 gallons
$60.10
 
 
 
   1-1/2 inch base rate fee for 8,520 gallons
$100.99
 
 
 
   2 inch base rate fee for 12,660 gallons
$150.06
 
 
 
   3 inch base rate fee for 20,400 gallons
$241.81
 
 
 
   4 inch base rate fee for 28,640 gallons
$333.91
 
 
 
   Additional usage is $1.86 per thousand gallons
WATER SYSTEM DEVELOPMENT FEE
Size
Multiplier
Development Fee
Installation Cost
Total
   3/4 inch
1
$1,118.46
$1,516.99
$2,635.45
   1 inch
1.69
$1,890.20
$1,786.88
$3,677.08
   1-1/2 inch
2.84
$3,176.43
*
   2 inch
4.21
$4,708.72
*
   3 inch
6.80
$7,605.53
*
   4 inch
9.39
$1,0502.34
*
*actual cost