All drawings and plans for the construction, erection, repair or alteration of any building or other structure for which a permit is required, having been received by the Building Commissioner shall, prior to the issuance of a permit, be presented to the Site Plan Review Committee, Code Enforcement Officer, electrical inspector, plumbing inspector and Fire Chief for examination and approval with regard to such provisions of the Village ordinances as are within the jurisdiction of their departments. Each officer or committee shall:
(A) Endorse approval of the plans on the face of the plans.
(B) Report in writing reasons for not approving the plans with required changes to the Building Commissioner, within three (3) business days.
(C) When objections have been satisfied, approve the plans as above. (Ord. 2005-24, 1-19-2006)