10-19-7: EFFECT OF APPROVAL OR DENIAL:
   A.   Approval of the planned development permit by the board of trustees authorizes the applicant to proceed with any necessary applications for building permits, certificates of occupancy, and other permits which the village may require for the proposed development. The zoning administrator shall review applications for these permits for compliance with the terms of the planned development permit granted by the board of trustees. No permit shall be issued for development which does not comply with the terms of the planned development permit.
   B.   The village board shall direct the zoning administrator to revise the official zoning map to reflect the existence and boundaries of each planned development permit granted.
   C.   An approval of a planned development permit by the board of trustees shall be null and void if the recipient does not file an application for a building permit for the proposed development within nine months after the date of adoption of the zoning ordinance approving the development permit.
   D.   An approval of a planned development permit by the board of trustees shall be null and void if construction has not commenced within fifteen months and is not completed within thirty three months after the date of adoption of the zoning ordinance approving the planned development permit.
   E.   An approval of a planned development permit with a phasing plan shall be null and void if construction has not commenced or is not completed in accordance with the terms of that phasing plan.
   F.   An approval of a planned development permit with a master plan shall be null and void if construction has not commenced or is not completed in accordance with the terms and conditions contained in the master plan.
   G.   An extension of the time requirements stated in subsections C, D, and E of this section may be granted by the board of trustees for good cause shown by the applicant, provided a written request is filed with the village at least four weeks prior to the respective deadline.
   H.   A planned development permit shall be null and void if the use or combination of uses for which the approval was granted ceases for a period of one year.
   I.   No application for a planned development which was previously denied by the board of trustees shall be considered by the development review board or the board of trustees if it is resubmitted in substantially the same form and/or content within two years of the date of such prior denial.
      1.   The zoning administrator shall review the application for a planned development and determine if the application is or is not substantially the same. An applicant has the right to request a hearing before the village board to appeal the determination of the zoning administrator, provided a petition for appeal is filed in writing to the zoning administrator within ten days of the decision.
      2.   The board shall affirm or reverse the determination of the administrator regarding whether the new application is in substantially the same form within thirty days of receipt of a petition for appeal.
      3.   If it is determined that the new application is not substantially in the same form, then the applicant is entitled to submit an application and have it reviewed in accordance with the provisions of section 10-19-5 of this chapter. (Ord. 3587, 2-29-2016)