§ 95.54 COMPLETION OF IMPROVEMENTS.
   (A)   Completion.
      (1)   The applicant shall complete required improvements before final building inspection or the issuance of an occupancy permit.
      (2)   If the applicant fails to complete the required improvements within the specified time, the Public Works Director may, at his or her option, cause the uncompleted improvements to be completed and the parties executing the performance security shall be firmly bound for the payment of all necessary costs.
   (B)   Extensions.
      (1)   The Public Works Director may extend the completion date upon written request by the applicant and the submittal of adequate evidence to justify the extension. The request shall be made at least 30 days before the expiration of the building permit or encroachment permit.
      (2)   The developer shall pay the costs incurred by the city in processing the extension request and extension agreement.
(Ord. 2008-002, passed 3-10-08)