1325.07 FEES FOR ELECTRICAL WORK.
   The fees in this section are subject to the assessment set forth in Section 1325.11. All permits are non-refundable.
 
(a) Residential Dwelling Structures
Residential
Non-
Residential
(1) New electrical systems
Per each dwelling unit
Additional fees
$130.00
Exempt
(2) Addition to electrical systems
Base fee for each dwelling unit affected
* Plus additional fees
$35.00
(3) Alterations to electrical systems (rehabilitation, damage repair and fire damage)
Base fee for each dwelling unit affected
* Plus per each 100 sq. ft. or fraction thereof of gross floor area
$35.00
$5.00
(4) New construction of; addition to; alteration to; electrical system of appurtenant building or structure
Base fee
* Plus additional fees
$35.00
TBD at the
discretion of
Building
Commissioner
(5) Repair of electrical systems
Per building or structure
Additional fees
$35.00
TBD at the
discretion of
Building
Commissioner
(6) Security, Communication and Sound System wiring
$50.00
 
(b) Non-Residential Dwelling Structures
Residential
Non-
Residential
(1) New electrical systems
Base Fee
* Plus per each 100 sq. ft. or fraction thereof of gross floor area
$120.00
$4.00
(2) Addition to electrical systems
Base fee
* Plus per each 100 sq. ft. or fraction thereof of gross floor area
$120.00
$4.00
(3) Alterations to electrical systems
Base Fee
* Plus additional fees in Section (C)
$120.00
TBD
(4) Repair of electrical systems
Per building or structure
Additional fees
$100.00
Exempt
(5) Security, Communication and Sound System Wiring
$125.00
   
(c) Additional Fees
Residential
Non-
Residential
Each switch
$0.50
$0.50
Each lighting outlet of 110/240 volts
$0.50
$0.50
Each lighting fixture of 110/240 volts
$0.50
$0.50
Each receptacle of 110/40 volts other than lighting
$0.50
$0.50
Each receptacle of greater than 240 volts and/or 1,000 watts
$5.00
$5.00
Each fixture greater than 1,000 watts
$5.00
$5.00
Each lighting outlet; each receptacle and/or outlet; each fixture of less than 100 volts
$0.50
$0.50
Each mast/meter base
$30.00
$50.00
Each main panel of 100 volts or greater
$30.00
$50.00
Each sub panel of 110 volts or greater
$15.00
$15.00
Each panel/ sub panel of less than 110 volts
$15.00
$15.00
Each generator
Note: Additional fuel gas permit may be required
$30.00
$40.00
Temporary lighting, receptacle and/or outlet installation
$30.00
$40.00
Temporary lighting and exit signage for tent structures
$30.00
$40.00
Electric sign
$45.00
Each new power bus duct
Per foot or fraction thereof of length
$0.50
Each new motor
Less than one horsepower
One to ten horsepower
More than ten horsepower
No charge
$5.00
$10.00
No charge
$10.00
$20.00
Underground service wiring
$25.00
$50.00
Optical fiber cable system; communication system and similar systems
Base fee per system
* Plus per each 1,000 sq. ft. or fraction thereof of gross area exceeding 5,000 sq. ft. system
$40.00
$20.00
$50.00
$30.00
Co-generation systems and associated equipment
$100.00
$100.00
Parking lot lighting per pole
$20.00
   
 
(d) Additional Penalty Fees
Residential
Non-
Residential
(1) Where work is begun without first obtaining a permit and paying the fee as indicated above, the applicant for a permit shall be charged a fee of triple the amount of the fee indicated in this section.
--
--
(2) Re-inspection of same item
$50.00
$50.00
(3) Inspection call and appearance of inspector on property and work not ready
2nd offense, inspection call, work not ready.
$100.00
$100.00
(4) Work covered without inspection
$50.00
$50.00
(Ord. 98-2018. Passed 2-12-19.)