A. A project applicant shall complete the water efficient landscape worksheet in Appendix B which contains information on plant factor, irrigation method, irrigation efficiency, and area associated with each hydrozone. Calculations are then made to show that the evapotranspiration adjustment factor (ETAF) for the landscape project does not exceed a factor of 0.55 for residential areas and 0.45 for non-residential areas, exclusive of special landscape areas. The ETAF for a landscape project is based on the plant factors and irrigation methods selected. The maximum applied water allowance is calculated based on the maximum ETAF allowed (0.55 for residential areas and 0.45 for non-residential areas) and expressed as annual gallons required. The estimated total water use (ETWU) is calculated based on the plants used and irrigation method selected for the landscape design. ETWU must be below the MAWA.
1. In calculating the maximum applied water allowance and estimated total water use, a project applicant shall use the ETo values from the reference evapotranspiration table in Appendix A. For geographic areas not covered in Appendix A, use data from other cities located nearby in the same reference evapotranspiration zone, as found in CIMIS reference evapotranspiration zones map, department of water resources, 1999.
B. Water budget calculations shall adhere to the following requirements:
1. The plant factor used shall be from WUCOLS or from horticultural researchers with academic institutions or professional associations as approved by the California department of water resources (DWR). The plant factor ranges from 0 to 0.1 for very low water using plants, 0.1 to 0.3 for low water use plants, from 0.4 to 0.6 for moderate water use plants, and from 0.7 to 1.0 for high water use plants.
2. All water features shall be included in the high water use hydrozone and temporarily irrigated areas shall be included in the low water use hydrozone.
3. All special landscape areas shall be identified and their water use calculated as shown in Appendix B.
4. ETAF for new and existing (non-rehabilitated) special landscape areas shall not exceed 1.0. (Ord. 2917, 2021: Ord. 2724 § 1, 2009)