The following permit requirements may apply to certain regulated earth disturbance activities, and must be met prior to commencement of regulated earth disturbance activities, as applicable:
A. All regulated earth disturbance activities subject to permit requirements by DEP under regulations at 25 Pa. Code, Chapter 102.
B. Work within natural drainageways subject to permit by DEP under 25 Pa. Code, Chapter 105.
C. Any stormwater management facility that would be located in or adjacent to surface waters of the commonwealth, including wetlands, subject to permit by DEP under 25 Pa. Code, Chapter 105.
D. Any stormwater management facility that would be located on a state highway right- of-way, or require access from a state highway, shall be subject to approval by the Pennsylvania Department of Transportation (PennDOT).
E. Culverts, bridges, storm sewers or any other facilities which must pass or convey flows from the tributary area and any facility which may constitute a dam subject to permit by DEP under 25 Pa. Code, Chapter 105.