§ 54.43 COMPLETED WORK, APPROVAL.
   (A)   After all work authorized by permit under this chapter has been completed, it shall be inspected as provided in § 54.41 of this chapter, and if found to be in accordance with this chapter and all other applicable ordinances, then the Commission shall issue an approval certificate or tag.
   (B)   It shall be unlawful for any person to connect with or use any electric equipment or to supply electric current over the same until such approval certificate or tag is issued. It shall likewise be unlawful for any utility to connect or to cause to be connected any service or building for the supply of electric current until it has been notified by the Commission that the electric work has been inspected and approved and is ready for electric service.