Type Of Wireless Facility | Time Line For City Review (Per Federal Law) | Deemed Granted (Per Federal Law) | Type Of Permit |
Collocations or modifications/replacement of wireless transmission equipment at an existing wireless tower or base station that do not "substantially change the physical dimensions of the existing wireless tower or base station" section 6409(a) facilities Distributed antenna systems and small cells | 60 days after the application is submitted Can be extended by mutual agreement | Yes | Type 1 WCF permit Administrative review and approval by Planning and Development Services Director and/or his/her designee |
Other collocations that "substantially change the physical dimensions of the existing wireless tower or base station" Roof mounted that do not qualify as existing base stations not to exceed 10 feet above the highest portion of the roof | 90 day review after application submitted | No | Type 2 WCF permit required See section 15.42.090 of this chapter for zoning restrictions |
New tower (not in public right-of-way) Roof mounted exceeding 10 feet above the highest portion of the roof | 150 days after application submitted | No | Type 3 WCF permit See section 15.42.090 of this chapter for zoning restrictions |
(Ord. 3025, 2019)