§ 54.016  INFORMATION REQUIRED PRIOR TO CONNECTION TO SYSTEM.
   (A)   All industrial users proposing to connect to or to contribute to the sewage works shall submit information on the use, processes and wastewater to the Director before connecting to or contributing to the sewage works. The information submitted must be sufficient for the YCUA to determine the impact of the user’s discharge on the sewage works and the need for pretreatment.
   (B)   The user shall submit, in units and terms appropriate for evaluation, the following information:
      (1)   The name, address and location of the user;
      (2)   The SIC number according to the Standard Industrial Classification Manual, Bureau of the Budget, 1972, as amended and the industrial category subject to national categorical pretreatment standards, 40 C.F.R., Chapter 1, Subchapter N, Part 403, if applicable;
      (3)   Wastewater constituents and characteristics including but not limited to those pollutants mentioned in §§ 54.001 through 54.004 of this code of ordinances and §§ 54.015 through 54.033, 54.045 through 54.055, 54.070 through 54.081, when required by the Director, as determined by a reliable analytical laboratory. Sampling and analysis shall be performed in accordance with the techniques prescribed in 40 C.F.R. part 136 (March 26, 2007), as amended from time to time. Where 40 C.F.R. part 136 (March 26, 2007) does not contain sampling or analytical techniques for the pollutant in question, or where the E.P.A. determines that the part 136 (March 26, 2007) sampling and analytical techniques are inappropriate for the pollutant in question, sampling and analysis shall be performed by using validated analytical methods of any other applicable sampling and analytical procedures, including procedures suggested by the publicly owned treatment works or other parties, approved by the E.P.A.;
      (4)   The time and duration of contribution;
      (5)   The average daily wastewater flow rates, including daily, monthly and seasonal variations, if any;
      (6)   Site plans, floor plans, mechanical and plumbing plans and details to show all sewers, sewer connections and appurtenances by the size, location and elevation, if the user is a SIU or as required by the YCUA;
      (7)   A description of activities, faculties and plant processes on the premises including all materials, which are or could be discharged;
      (8)   The nature and concentration of any pollutants in the discharge which are limited by any YCUA, state or federal pretreatment standards, and a statement regarding whether or not the pretreatment standards are being met on a consistent basis and if not, whether additional operation and maintenance and/or additional pretreatment is required by the industrial user to meet applicable pretreatment standards;
      (9)   If additional pretreatment and/or O&M will be required to meet the pretreatment standards, the shortest schedule by which the user will provide additional pretreatment shall be provided. The completion date in this schedule shall not be later than the compliance date established for the applicable pretreatment standard. The following conditions shall apply to this schedule:
         (a)   The schedule shall contain increments of progress in the form of dates for the commencement and completion of major events leading to the construction and operation of additional pretreatment required for the user to meet the applicable pretreatment standards;
         (b)   No increment referred to in division (B) shall exceed nine months; and
         (c)   Not later than 14 days following each date in the schedule and the final date for compliance, the user shall submit a progress report to the Director including, as a minimum, whether or not it complied with the increment of progress to be met on the date and, if not, the date on which it expects to comply with this increment of progress, the reason for delay and the steps being taken by the user to return the construction to the schedule established. In no event shall more than nine months elapse between such progress reports to the Director.
      (10)   Each product produced by type, amount, process or processes and rate of production;
      (11)   The type and amount of raw materials processed, average and maximum per day;
      (12)   The number and type of employees, hours of operation of plant and proposed or actual hours of operation of pretreatment system; and
      (13)   Any other information as may be deemed by the Director to be necessary to evaluate the impact of the discharge on the sewage works.
(Prior Code, § X-3.44)