(A) Builder/Developer submits application and plans with appropriate application fee. All materials shall be submitted using the Village’s Online Permit Center;
(B) Staff reviews all applications for completeness and compliance in accordance with the Pinehurst Development Ordinance. Staff has ten (10) working days to determine compliance or provide written comments on the application stating the deficiencies;
(C) When staff determines that the application is complete and in compliance with the Pinehurst Development Ordinance, a development permit shall be issued;
(D) Applicant may then apply for a building permit (at the discretion of the applicant, building permits may be applied for prior to the issuance of the development permit, but a building permit shall not be issued prior to a development permit);
(E) Throughout construction, exterior changes may occur. All changes must be resubmitted to the Planning and Inspections Department and be reviewed for compliance;
(F) If the structure has a permanent foundation (or is a swimming pool) and is shown to be within five (5) feet of the setback on the approved plans a final survey in addition to the foundations survey shall be provided showing compliance.
(G) Upon the completion of the project the Village Planner will conduct a compliance inspection and sign off on a certificate of occupancy if required.
(H) Flow Chart for Path on Single Family Residential Plans
(Ord. 21-14, passed 10-26-2021)