(A) Appendix B of this Ordinance contains the checklist to be used by the applicant as well as the staff in the review and permit authorization process;
(B) A foundation survey is required prior to construction above the foundation if it is shown on the submitted plan that the structure is within five (5) feet of the required setback and the structure has a permanent foundation or is a swimming pool.
(C) Revisions and changes will be considered and approved or disapproved by the Village Planner. Examples of changes are site plan, landscape plan, change of height or the addition of elements not previously shown. All proposed changes shall be submitted in electronic format to the Village Planner. The staff will evaluate the proposed changes and provide a response to the applicant. For all changes, redrawing of plans shall be required.
(Ord. 21-14, passed 10-26-2021)