8.04.070   Construction in compliance with approved plans.
   All work shall conform to approved plans and specifications. Should it be necessary or desirable to make any material change in the design of the approved establishment which will affect the capacity, hydraulic conditions, flow, an operating unit or sanitary feature of the proposed work, revised plans and specifications, together with a written statement of the reason for the change, must be submitted to the health officer for review, and approval must be obtained in writing before the work affected by the change is undertaken. Minor revisions not affecting the capacity, hydraulic conditions, flow, operating unit or sanitary feature will be permitted during construction without further approval but plans clearly showing such alterations must be filed with the department at the completion of the entire project.
(Ord. 2016-12, § 1 (part), 2016)