Depending on the type and complexity of a proposed impact on a District Facility, the following special conditions may be included on the Facility Impact Permit:
A. Pre-construction meetings.
B. Special mix designs.
C. Shop drawings.
D. Third party materials testing.
E. Material certifications.
F. Specific inspection milestones, including final walkthrough inspection.
(Ord. 2018-FC1 § 1 (part), 2018)