A. Structural flood control measures may be proposed in conjunction with, or in place of, detention/retention systems if it can be clearly demonstrated that such measures will not alter the water and sediment equilibrium and storm water quality of the affected watercourse, and will mitigate environmental impacts.
B. Appropriate structural flood control measures, such as channelization to a logical conclusion downstream of the proposed development and/or improvements to existing offsite flood control systems within the applicable drainage or stream reach, shall be completed in accordance with plans reviewed and approved by the chief engineer.
(Ord. 2010-FC5 § 1 (part), 2010; Ord. 1999 FC-1 § 1 (part), 1999; Ord. 1988 FC-2 Art. 14 (B), 1988)