1294.14   TIME LIMITATION FOR BEGINNING OF CONSTRUCTION.
   After issuance of a permit to construct a wireless tower or antenna, the permit holder shall begin construction within 180 days and shall complete construction within 360 days or the permit and approval shall expire. In the case of City-owned or public property, the Planning and Zoning Commission shall require the permit holder to certify that if construction is not commenced within 180 days or completed within 360 days, the site shall be available for another wireless communications facility provider. Should such delay in beginning or completing construction be due to force majeure, the delayed party shall take all necessary and reasonable steps to overcome the force majeure and shall keep the City advised of the reason for the delay and the steps being taken to reduce the delay. If the delay is due to force majeure, the City and the delayed party shall agree to a new construction date which new date shall then be subject to the time limits as stated in this section.
(Ord. 2014-27. Passed 8-5-14.)