(a) The opening and restoration of the surface of the right-of-way shall be performed in accordance with rules, regulations and specifications promulgated by the Manager. No person shall fail to comply with the rules, regulations and specifications so promulgated by the Manager.
(b) Upon failure or refusal of the permittee to satisfactorily fill the excavation, restore the surface and remove all excess materials within the time specified in the permit, or, where not specified therein, within a reasonable time after commencement of the work, the Municipality may proceed without notice to make such fill and restoration. The cost of the City’s work in such cases shall be paid by the permittee within fifteen days of demand by the City. Until such bill is paid, no further permits shall be issued to the permittee.
(Ord. 98-08. Passed 2-3-98.)