(a) Pre-Application Meeting: The owner shall attend a Pre-Application Meeting with the City Engineer to discuss the proposed project, review the requirements of this regulation, identify unique aspects of the project that must be addressed during the review process, and establish a preliminary review and approval schedule.
(b) Preliminary Comprehensive Stormwater Management Plan: The owner applicant shall submit two (2) sets of a Preliminary Comprehensive Stormwater Management Plan (Preliminary Plan) and the applicable fees to the building department. The Preliminary Plan shall show the proposed property boundaries, setbacks, dedicated open space, public roads, water resources, stormwater control facilities, and easements in sufficient detail and engineering analysis to allow the City Engineer to determine if the site is laid out in a manner that meets the intent of this regulation and if the proposed SCMs are capable of controlling runoff from the site in compliance with this regulation. The owner shall submit two (2) sets of the Preliminary Plan and applicable fees as follows:
(1) For subdivisions: In conjunction with the submission of the preliminary subdivision plan.
(2) For other construction projects: In conjunction with the application for a building permit.
(3) For general clearing projects: Prior to commencement of any clearing/demolition activities or in conjunction with the application for an applicable permit.
(c) Final Comprehensive Stormwater Management Plan: The owner shall submit two (2) sets of a Final Comprehensive Stormwater Management Plan (Final Plan) and the applicable fees to the building department in conjunction with the submittal of the final plat, improvement plans, or application for a building permit for the site. The Final Plan shall meet the requirements of Section 1510.08 and shall be approved by the City Engineer prior to approval of the final plat and/or before issuance of a building permit by the City Building Inspector.
(d) Review and Comment: The City Engineer shall review the Preliminary and Final Plans submitted, and shall approve or return for revisions with comments and recommendations for revisions. A Preliminary or Final Plan rejected because of deficiencies shall receive a narrative report stating specific problems and the procedures for filing a revised Preliminary or Final Plan.
(e) Approval Necessary: Land clearing and soil-disturbing activities shall not begin and zoning and/or building permits shall not be issued without an approved Comprehensive Stormwater Management Plan.
(f) Sublots Will Not Proceed: Comprehensive Stormwater Management Plans for individual sublots in a subdivision will not be approved and building permits will not be issued unless the larger common plan of development or sale containing the sublot is in compliance with this regulation.
(g) Valid for Two Years: Approvals issued in accordance with this regulation shall remain valid for two (2) years from the date of approval. (Ord. 2017-36. Passed 11-15-17.)