(A) Public utility companies may apply for an annual blanket permit with the Public Works Department, allowing an unlimited number of permits for all activities that do not disturb the asphalt surface of a town-maintained public road. However, public utility companies shall provide the Public Works Department a weekly report detailing activities performed, such as the location of the activity and the type of work performed. Plans are not required for routine maintenance and service connections.
(B) Public utility companies that do not desire to apply for an annual blanket permit shall apply for a separate permit for each activity within a town-maintained road right-of-way together with applicable fees and/or security.
(C) Regardless of whether a utility company has obtained an annual blanket permit, separate permits are required for new or replacement line installations, new or relocated service poles, and any activity disturbing the asphalt surface of a town-maintained public road.
(Ord. 21-07, passed 8-2-21)