(A) Where a preliminary plat is presented to the Planning and Zoning Board showing that the developer proposes to excavate or create waterways in connection with the development concerned in the plat, the developer shall submit, along with the preliminary plat, the following data.
(1) Locations and dimensions of the excavations or waterways.
(2) Typical cross section showing the elevation of perimeter or banks, grade of slopes, water level at mean low water, depth of excavation, and bottom width.
(3) A topographical survey of the subject property prepared by a registered land surveyor licensed to practice in the state.
(4) An estimate of the amount of material to be excavated certified by a registered engineer licensed to practice in the state.
('69 Code, § 14-7)
(B) The City Commission may waive or vary the strict requirements of the waterways regulations of this chapter by five affirmative votes when it deems it to be in the public interest or where unnecessary hardship would occur to the landowner because of the strict enforcement of these regulations.
('69 Code, § 14-10)
(Ord. 127, passed 11-15-65; Am. Ord. 2021-02, adopted 3-17-21; sought to be reconsidered, Commission passed 4-21-2021)
Cross-reference:
Waterways excavation bond, see § 154.15
Final plat requirements, see § 154.30
Design standards for waterways, see § 154.31