1354.09 ENFORCEMENT.
   If no development has occurred pursuant to the approved final plat:
   (a)    Within twelve months after the date of the adoption of the Planned Neighborhood Development, or
   (b)    Upon expiration of any extension of time for starting development granted by the Planning Commission,
the approved final plat shall become null and void with a new preliminary plat and public hearing request for any development on the project site.
   After general construction commences, the Planning Director shall review at least once every six months all building permits issued and compare them to the overall development schedule submitted in Section 1354.07. If the Planning Director determines that the rate of construction of residential units or nonresidential structures differs substantially from the development schedule, he shall notify the developer and the Director of Code Administration in writing and upon continued violation may suspend the issuance of building permits of dwelling units or nonresidential structures until compliance is achieved.
(Ord. 0-418. Passed 11-12-85.)