§ 91.52 REQUIRED PERMIT TO DEMOLISH DOES NOT EXTEND COMPLIANCE TIME.
   (A)   When abatement of a violation is achieved through demolition, a permit shall be obtained from the city.
   (B)   The completion time shall correspond to the correction time allowed in the notice of violation issued by the code official.
   (C)   It shall be the duty of the violator to notify the code official that additional time is needed and to provide justification why the completion time is inadequate.
   (D)   The code official may extend the completion time, in his or her sole discretion, if he or she determines that the completion time is not reasonable given the facts of a particular violation.
   (D)   Any cessation of the demolition may cause the permit to become invalid.
(Ord. 682, passed 5-12-2009)