A CDDL shall be considered closed after the following have occurred:
(A) The CDDL does not accept any additional quantities of waste;
(B) The CDDL is properly capped, mulched, seeded and fertilized;
(C) The CDDL cap and all disturbed areas associated with the CDDL construction have obtained 90% vegetative ground coverage;
(D) Leachate production has ceased or tested parameters are below the appropriate state groundwater or surface water standards for two testing periods;
(E) The operator has submitted an as-built survey and site plan of the CDDL showing the final elevation contours of the CDDL cap. The site plan shall show the final volume of the landfill with and without the cap material. The site plan shall also follow the specification outlined in § 50.098; and
(F) The Solid Waste Coordinator has conducted the final inspection of the CDDL.
(Ord. KOC 97-830-53, passed 9-2-1997)